Canada’s nuclear watchdog green-lights operation of aging Pickering reactors to 2026
[ https://www.theglobeandmail.com/busines ... pickering/ ]
Matthew McClearn October 11, 2024
EXCERPT: "Canada’s nuclear safety regulator again extended a crucial permit for the country’s oldest nuclear power plant on Friday, allowing it to continue operating beyond its original design life.
On Friday the Canadian Nuclear Safety Commission authorized its owner, Ontario Power Generation, to operate the Pickering Nuclear Generating Station for an additional two years, to Dec. 31, 2026. The extended permit applies only to its newest four reactors, Units 5 through 8, which are collectively known as Pickering B. Those reactors entered service between 1983 and 1986.
The licence extension was granted by commissioners Timothy Berube, Marcel Lacroix and Andrea Hardie, who decided OPG would make adequate provisions for protecting the environment and public safety.
Canada’s homegrown reactor, the CANDU, was originally assigned a design life of 30 years, which had been incorporated into CNSC licensing requirements. If followed, they would have dictated that all four reactors shut down for major overhauls or decommissioning years ago. The CNSC, though, amended those rules and extended the station’s licence three times, while imposing more thorough inspection requirements on key components. The Pickering B reactors are now around 40 years old. . . . "